What is a transmittal — and why it is the most valuable boring document you own
A transmittal is a list of what you sent, to whom, and when. It is dull, it takes four minutes, and it is the document that decides who pays when the wrong revision gets built.
A transmittal is a record of an issue: these drawings, at these revisions, went to these people, on this date, for this purpose. That is all it is. It is the least interesting document in a project and the one most likely to save a practice a six-figure argument.
What goes on it
- A transmittal number, so it can be referred to
- The date issued
- Who it went to — organisation and individual, not "the contractor"
- Every drawing number AND its revision letter
- The purpose: for information, for comment, for approval, for construction
- The medium — a printed set and a PDF are different events
The purpose line is the one people skip and the one that matters most. "For construction" and "for comment" carry entirely different liability, and a set issued for comment that somebody built from is a very different conversation if the transmittal says so.
Why an email is not a substitute
An email can be a record, and on a small project it often is enough. It stops being enough at the point where you need to answer a question about a project, not a question about a mailbox: which revision is current on site, what did we issue in March, has the structural engineer ever received Rev D.
Those are register questions. A mailbox answers them by search, in an afternoon, incompletely. A transmittal register answers them by looking, in seconds, completely — and that difference is the whole reason document control exists as a discipline.
The argument this prevents
A contractor builds from Rev B. Rev D is current. Work is demolished and rebuilt. The only question that matters is whether Rev D was issued to them, and when.
With a transmittal register that question takes thirty seconds and the answer is not disputable. Without one it takes a fortnight of letters, during which the site is stopped and both parties are accruing cost — and it is usually settled by whoever kept better records rather than by who was right. See version history is not revision control.
A workable habit for a small practice
- Nothing leaves the office without a transmittal, including a PDF sent from a phone
- One numbering sequence per project, never per person
- The revision letter is on the transmittal, not just on the drawing
- Superseded revisions stay in the register, marked superseded, forever
- The register is somewhere more than one person can read
That last point is the one that fails. A register maintained in one person's folder is a register that stops existing when they are on leave.
In Ofivio, issuing a drawing set produces the transmittal — the register is a consequence of the issue rather than a separate discipline.
See drawing management →Drawing revision management — version history is not revision control
The most expensive failure in a small practice is a revision that did not reach site. It is almost never anybody's fault, which is exactly why process cannot fix it and a system has to.
DesignWhat an architect actually hands over at completion
Projects rarely end. They stop being urgent, and the last ten per cent trails for months because nobody wrote down what finishing means.
DesignGetting client approvals in writing — without making the client do paperwork
"But we agreed to this in the meeting" is the most expensive sentence in architecture. Approvals are the practice's only protection against free redesign — and they have to be effortless for the client, or they won't happen.